This prototype is password protected
Enter the password to continue.
Basics
Complete
Overview
- Commitment #
- CRS-Com-9
- Title
- Upgrade PIT-tag detection arrays at Fernbridge Dam
- Source
- Basin Fish Passage Biological Assessment - Proposed Action
- Section
- 2.7.1.2
- Page
- 2-120
- Category
- Hydro
- Subcategory
- RM&E
- Commitment type
- Functional
- Frequency
- Discrete
- Description
- Add PIT-tag detection capability to two additional fish ladders at Fernbridge Dam.
- Interpretation
- Install and commission detection arrays capable of reading existing tag formats.
- Implementation
- BPA funds equipment procurement; the Corps installs and maintains the arrays.
- Notes
- Commissioning completed ahead of schedule in 2024.
- Other associated commitments
- Start date
- 10/1/2021
- End date
- 9/30/2024
- Deliverable
- Installation Report
- Deliverable frequency
- Once
- Document due date
- 12/31/2024
Responsible parties
- Lead agency
- BPA
- Partner agency
- USACE
- Partner POC
- Renee Ashford
- Policy lead
- Marcus Feld
- BiOp SME
- Dana Iverson
- COR
- Todd Whitfield
- NMFS POC
- Alan Cho
- Associated projects
- PRJ-2019-018
Commitment status by year
2021 Not Started
2022 In Progress
2023 In Progress
2024 Complete
2025 Complete
2026now Complete
2027 Complete
2028 Complete
2029 Complete
2030 Complete
2031 Complete
2032 Complete
2033 Complete
2034 Complete
2035 Complete
Commitment documents
No due dates or documents yet
Add a discrete due date, a recurring due date, or upload a document with no due date.
A commitment can have discrete due dates or one recurring due date, not both. An individual recurring occurrence can only be edited or deleted as part of the whole series.
Recurring due date: starts , every .