QA

Far-field through-Delta survival & routing

SUB-022

Identity

NameFar-field through-Delta survival & routing
IDSUB-022
COA reference10.19.1b
ParentMigration & Survival Study

Timing

Rolled-up spanOct 2026 – Oct 2031min start → max end across all tasks in this branch
Water yearsWY2027–WY2032

Funding plan

Planned$3.0M · WY2027–2032
Water yearOwnRolled upTotal
WY2027—$120k$120k
WY2028—$440k$440k
WY2029—$990k$990k
WY2030—$550k$550k
WY2031—$710k$710k
WY2032—$160k$160k
Total$0$3.0M$3.0M

Status roll-up

Rolled up from 4 tasksBlocked
4 tasks3 on track0 at risk1 blocked
Constraints & notes
  • Back-scheduled from in-water construction (WY2034)
  • Requires ≥3 tag-release years before model fit
SUB-022Edit record
Funding — own entries
WY2027
WY2028
WY2029
WY2030
WY2031
WY2032
Help & Guidance

Beacon

On this page

Terms

Page