QA

Far-field through-Delta survival & routing

SUB-022

Identity

Name Far-field through-Delta survival & routing
ID SUB-022
COA reference 10.19.1b
Parent Migration & Survival Study

Timing

Rolled-up span Oct 2026 – Oct 2031 min start → max end across all tasks in this branch
Water years WY2027–WY2032

Funding plan

Planned $3.0M · WY2027–2032
Water year Own Rolled up Total
WY2027 $120k $120k
WY2028 $440k $440k
WY2029 $990k $990k
WY2030 $550k $550k
WY2031 $710k $710k
WY2032 $160k $160k
Total $0 $3.0M $3.0M

Status roll-up

Rolled up from 4 tasks Blocked
4 tasks 3 on track 0 at risk 1 blocked
Constraints & notes
  • Back-scheduled from in-water construction (WY2034)
  • Requires ≥3 tag-release years before model fit
SUB-022 Edit record
Funding — own entries
WY2027
WY2028
WY2029
WY2030
WY2031
WY2032