Survey Protocol Approval

Type
Action List
Project
Delta Conveyance
Exported
2026-10-19
Actions
2
ActionFrequencyCommitments
Plan
Submit Preconstruction CTS Burrow Watering ProtocolOne timeCOA 11.42.1
Submit Species and Habitat Survey Protocols to CDFWOne timeCOA 6.1, COA 11.38

Plan

Submit Preconstruction CTS Burrow Watering Protocol

COA 11.42.1

Permittee prepares, in consultation with CDFW, a preconstruction watering protocol describing the water application method, duration, timing and quantity used to mimic rain and stimulate CTS emergence from burrows on permanently impacted construction sites, and submits it in the appropriate Construction Phase Authorization Package.

Frequency
One time
Twin Cities Complex
Not StartedDue 2026-09-25
Bouldin Island Geotechnical Exploration
In ProgressDue 2026-12-15

Submit Species and Habitat Survey Protocols to CDFW

COA 6.1, COA 11.38

Permittee develops with CDFW the final protocol-level species and habitat survey methodology for CTS, GGS, SWHA, TRBL, CBB and MALI, submits it in the Pre-implementation Phase Authorization Package, and obtains written approval before any Covered Activity including preconstruction field investigations and preconstruction species site surveys. The protocols specify survey number, timing and spacing, habitat types, methods and rationale, capture and identification protocols and presence or…

Frequency
One time
Timing
prior to initiation of any Covered Activity
Twin Cities Complex
In ProgressDue 2026-08-29
Bouldin Island Geotechnical Exploration
In ProgressDue 2026-06-29