Construction Surveys and Monitoring
- Type
- Action List
- Project
- Delta Conveyance
- Exported
- 2026-10-19
- Actions
- 22
| Action | Frequency | Commitments |
|---|---|---|
| Monitoring | ||
| Conduct Annual TRBL Survey During Construction | Recurring | COA 11.84 |
| Conduct Baseline and Annual In-Water Mercury Monitoring | Recurring | COA 11.30 |
| Conduct Photo Monitoring of Temporary Impact Areas | Recurring | COA 10.6 |
| Conduct Water Quality Evaluation Studies | Ongoing | COA 10.20, COA 10.20.2, COA 10.20.3, COA 10.20.4, COA 10.20.5 |
| Implement CDFW-Approved Subsurface Vibration Study | One time | COA 10.17 |
| Implement Covered Fish Species Monitoring and Science Program | Ongoing | COA 10.18 |
| Install Real-Time Water Quality Monitoring Station | One time | COA 10.20.1 |
| Notify Designated Representative of SWHA Nest Distress | As needed | COA 11.75 |
| Survey Riverbank and Vegetation Conditions at Barge Sites | Recurring | COA 11.36 |
| Verify Impact Multipliers in the Annual Status Report | Recurring | COA 12.1 |
| Survey | ||
| Complete Pre-Disturbance Habitat Photo Documentation | One time | COA 10.3 |
| Conduct and Report Annual GGS Surveys | Recurring | COA 11.56 |
| Conduct Annual MALI Surveys in Suitable Habitat | Recurring | COA 11.105, COA 11.107 |
| Conduct Baseline Invasive Plant Survey | One time | COA 11.19 |
| Conduct CTS Walking Clearance Survey Before Ground Disturbance | As needed | COA 11.42 |
| Conduct GGS Survey Before Exclusion Fencing Installation | As needed | COA 11.56 |
| Conduct Habitat Evaluation Field Survey | One time | COA 10.8 |
| Conduct Nesting-Season SWHA Survey Before Field Investigations | As needed | COA 11.78 |
| Conduct Post-Dewatering GGS Clearance Survey | One time | COA 11.61 |
| Conduct Pre-Activity CBB Foraging and Nest Surveys | Recurring | COA 11.97, COA 11.99, COA 11.100 |
| Flag Burrows and Habitat Features Before Earthmoving | One time | COA 11.49.1, COA 11.54, COA 11.62.1 |
| Fund and Implement the DS/LFS Spawning Habitat Study | One time | COA 10.21.5 |
Monitoring
Conduct Annual TRBL Survey During Construction
COA 11.84
The Designated Biologist surveys TRBL habitat each year Covered Activities are expected to occur in it, and Permittee reports each survey to CDFW in the Monthly Compliance Report and summarizes them in the Annual Status Report.
- Frequency
- Recurring
- Timing
- each year Covered Activities are expected to occur in TRBL habitat
- Twin Cities Complex
- In ProgressDue 2027-01-191 of 3 done
Conduct Baseline and Annual In-Water Mercury Monitoring
COA 11.30
Permittee evaluates baseline water quality before construction to characterize mercury sources and concentrations of mercury, methylmercury, organic carbon, iron and sulfate at each construction site, then implements MMMP mercury monitoring each year in-water Covered Activities occur, reporting results in the Monthly Compliance Report and summarizing them in the Annual Status Report.
- Frequency
- Recurring
- Timing
- each year in-water Covered Activities are expected to occur
- Byron Tract Forebay
- Not StartedDue 2027-04-262 of 3 done
- Intake B — North Delta
- In ProgressDue 2027-02-281 of 3 done
Conduct Photo Monitoring of Temporary Impact Areas
COA 10.6
Permittee photographs each established photo monitoring station before construction and every month until construction and initial restoration are complete, then every three months until restoration success is reached, visiting all stations within two days per cycle and delivering the images in a geographic format monthly with the Monthly Compliance Report and in full with the Annual Status Report.
- Frequency
- Recurring
- Timing
- each month thereafter until construction and initial restoration is complete, then every three months following the initial restoration until restoration success is reached
- Intake B — North Delta
- Not StartedDue 2026-08-151 of 3 done
Conduct Water Quality Evaluation Studies
COA 10.20, COA 10.20.2, COA 10.20.3, COA 10.20.4, COA 10.20.5
Permittee develops with CDFW and implements the sediment and turbidity, harmful algal bloom, selenium bioaccumulation and mercury study plans, running them from the preconstruction baseline period through Phase 2 Operations and evaluating results with the Covered Fish Species life cycle models against the Biological Criteria. Each study carries an adaptive element that expands effort if impacts are detected.
- Frequency
- Ongoing
- Timing
- continue implementation through Phase 2 Operations
- Bouldin Island Geotechnical Exploration
- In ProgressDue 2026-07-17
- Byron Tract Forebay
- Completed
Implement CDFW-Approved Subsurface Vibration Study
COA 10.17
Permittee implements the CDFW-approved Subsurface Testing and Monitoring Study Plan on surface and subsurface vibration effects on CTS, GGS and CBB before initiating Covered Activities at any Project site containing suitable habitat for those species. Results and the proposed vibratory monitoring protocols are carried into the Construction Phase Authorization Package.
- Frequency
- One time
- Byron Tract Forebay
- On HoldDue 2026-07-30
Implement Covered Fish Species Monitoring and Science Program
COA 10.18
Permittee funds, initiates and implements Covered Fish Species monitoring and science for DS, LFS, CHNWR, CHNSR and WS, beginning with at least five years of In-water Preconstruction Baseline Monitoring before in-water construction and continuing through In-water Construction, Phase 1 Operations and Phase 2 Operations Monitoring. Aquatic conditions assessments for each period feed the Phase 2 Authorization Package and the Final Mitigation Report.
- Frequency
- Ongoing
- Timing
- prior to Project in-water construction and throughout Project construction and operations (Phase 1 Operations and Phase 2 Operations)
- Bouldin Island Geotechnical Exploration
- In ProgressDue 2026-09-20
- Byron Tract Forebay
- In ProgressDue 2026-06-28
Install Real-Time Water Quality Monitoring Station
COA 10.20.1
Permittee funds, installs and maintains a real-time monitoring station downstream of north Delta Intake C, equipped like the CDEC Sacramento River at Hood station, before In-water Preconstruction Baseline Monitoring begins, and provides the data to CDFW in real time at 15-minute increments.
- Frequency
- One time
- Timing
- before initiation of In-Water Preconstruction Baseline Monitoring
- Byron Tract Forebay
- Completed
Notify Designated Representative of SWHA Nest Distress
COA 11.75
When the Designated Biologist determines that nesting SWHA within 0.5 mile of the construction site are in distress or showing abnormal nesting behavior from Covered Activities, the biologist stops the work and immediately notifies the Designated Representative.
- Frequency
- As needed
- Timing
- immediately notify Designated Representative
- Southern Forebay & Pumping Plant
- Overdue
- Twin Cities Complex
- On Hold
Survey Riverbank and Vegetation Conditions at Barge Sites
COA 11.36
A Fisheries Biologist or Biological Monitor visits each site requiring barges, including each north Delta intake and geotechnical exploration site, during the growing season before work begins, during construction, and annually for up to five years after construction, recording the extent of emergent and riparian vegetation, bank conditions on both riverbanks and general site conditions.
- Frequency
- Recurring
- Timing
- during the growing season prior to initiation of construction activities, during construction, and then annually for up to five years after construction
- Bouldin Island Geotechnical Exploration
- On HoldDue 2026-06-161 of 3 done
- Byron Tract Forebay
- Not StartedDue 2026-12-282 of 3 done
- Intake B — North Delta
- Not StartedDue 2027-01-012 of 3 done
Verify Impact Multipliers in the Annual Status Report
COA 12.1
Permittee verifies through Annual Status Report documentation of impacts and mitigation that the assumed impact multipliers for the 230 kV transmission lines and for preconstruction activities hold, comparing actual disturbance against the assumed tower footprint, work area and temporary surface impact shares.
- Frequency
- Recurring
- Timing
- Annual Status Report
- Southern Forebay & Pumping Plant
- Not StartedDue 2026-11-272 of 3 done
- Twin Cities Complex
- Not StartedDue 2027-06-022 of 3 done
Survey
Complete Pre-Disturbance Habitat Photo Documentation
COA 10.3
No more than 14 days before Covered Activities begin at a construction site, Permittee photographs each distinct suitable habitat area with at least five photographs per area, one each from the north, south, east and west plus one facing the area, separately for each Covered Species' habitat, and files the images in the GIS habitat tracking.
- Frequency
- One time
- Timing
- no more than 14 days prior to initiation of Covered Activities
- Bethany Reservoir Aqueduct
- Not StartedDue 2026-11-01
Conduct and Report Annual GGS Surveys
COA 11.56
After the Construction Phase Authorization Package is submitted, the Designated Biologist repeats the GGS survey each year Covered Activities are expected in GGS habitat or within three feet of it, and Permittee reports the results to CDFW in the Monthly Compliance Reporting and summarizes them in the Annual Status Report.
- Frequency
- Recurring
- Timing
- each year Covered Activities are expected to occur in GGS habitat
- Byron Tract Forebay
- On HoldDue 2027-01-051 of 3 done
Conduct Annual MALI Surveys in Suitable Habitat
COA 11.105, COA 11.107
Each year Covered Activities are expected in MALI habitat, and again before SCADA or transmission line maintenance and repair, the Designated Biologist or Biological Monitor repeats the MALI preconstruction survey so that non-disturbance buffers can be placed around any plants found.
- Frequency
- Recurring
- Timing
- shall occur each year Covered Activities are expected to occur in MALI habitat
- Southern Forebay & Pumping Plant
- Not StartedDue 2026-11-082 of 3 done
- Twin Cities Complex
- Not StartedDue 2026-06-051 of 3 done
- Bouldin Island Geotechnical Exploration
- In ProgressDue 2027-02-231 of 3 done
Conduct Baseline Invasive Plant Survey
COA 11.19
Before any Covered Activity starts at a construction site, a CDFW-approved Designated Biologist qualified in botanical surveys submits the sampling methodology to CDFW in the Phase Authorization Package and then conducts a qualitative and quantitative baseline survey of invasive plant type, location and abundance within the site using that methodology.
- Frequency
- One time
- Timing
- prior to the start of any Covered Activity
- Twin Cities Complex
- Not StartedDue 2026-11-06
- Bouldin Island Geotechnical Exploration
- Not StartedDue 2026-03-04
- Byron Tract Forebay
- In ProgressDue 2026-06-20
Conduct CTS Walking Clearance Survey Before Ground Disturbance
COA 11.42
Before any vegetation clearing or ground-disturbing Covered Activity, the Designated Biologist or Biological Monitor completes nocturnal walking or cover-board surveys giving 100 percent visual coverage of the construction site and its 75-foot boundary at every site in suitable upland habitat within 1.3 miles of a CTS breeding site, checking beneath woody debris and other refugia. Any CTS found is moved by the Designated Biologist under the CTS Relocation Plan.
- Frequency
- As needed
- Bouldin Island Geotechnical Exploration
- Overdue
- Byron Tract Forebay
- Not Started
Conduct GGS Survey Before Exclusion Fencing Installation
COA 11.56
Within 24 hours before exclusion fencing is installed, the Designated Biologist or Biological Monitor surveys the construction site and three-foot buffer with 100 percent visual coverage for GGS. If a snake is found, installation is delayed until it leaves on its own or is removed and relocated under COA 11.67.
- Frequency
- As needed
- Timing
- within 24 hours (one calendar day) preceding exclusion fencing installation
- Intake C — North Delta
- In Progress
- Bethany Reservoir Aqueduct
- Not Started
Conduct Habitat Evaluation Field Survey
COA 10.8
The Designated Biologist field-surveys the planned construction site and accessible land within 1,300 feet of it to identify suitable habitat for each Covered Species as defined in COA 10.4. The initial results, the spatial extent of suitable habitat per species and the total area surveyed are included in the Construction Phase Authorization Package.
- Frequency
- One time
- Bethany Reservoir Aqueduct
- OverdueDue 2026-05-12
Conduct Nesting-Season SWHA Survey Before Field Investigations
COA 11.78
When preconstruction field investigations must occur during the SWHA nesting season, the Designated Biologist surveys the preconstruction activity site and the area within 0.5 mile for nesting SWHA before those activities begin.
- Frequency
- As needed
- Intake C — North Delta
- In Progress
- Bethany Reservoir Aqueduct
- On Hold
Conduct Post-Dewatering GGS Clearance Survey
COA 11.61
After aquatic habitat is dewatered, the Designated Biologist surveys all suitable GGS aquatic and upland habitat within the construction site that lies outside established ESAs, and relocates any GGS observed under the GGS Relocation Plan.
- Frequency
- One time
- Intake C — North Delta
- In ProgressDue 2026-04-07
- Bethany Reservoir Aqueduct
- Not StartedDue 2026-06-19
Conduct Pre-Activity CBB Foraging and Nest Surveys
COA 11.97, COA 11.99, COA 11.100
Before ground disturbance or vegetation removal in suitable CBB habitat during the colony active period (February 1 to October 31, or until flowering vegetation is largely desiccated), the Designated Biologist with Biological Monitor assistance runs at least three protocol surveys beyond the baseline, spaced two to four weeks apart with the last within 72 hours of construction, in every year work occurs in or within 50 feet of suitable habitat, and repeats the surveys in undisturbed habitat…
- Frequency
- Recurring
- Timing
- at least three surveys, spaced two to four weeks apart, with the last survey within 72 hours prior to construction activity, each year Covered Activities occur in or within 50 feet of suitable CBB habitat
- Byron Tract Forebay
- On HoldDue 2026-07-121 of 3 done
- Intake B — North Delta
- In ProgressDue 2026-11-251 of 3 done
Flag Burrows and Habitat Features Before Earthmoving
COA 11.49.1, COA 11.54, COA 11.62.1
At least five days before earthmoving in an area, the Designated Biologist or Biological Monitor identifies and flags all potential burrows, soil cracks, crevices and other habitat features that lie within the construction site but outside the planned direct-disturbance footprint, including all avoidable burrows, demarcates areas of high burrow concentration for avoidance, and uses signs, stakes or flags clearly distinguishable from work-area markings.
- Frequency
- One time
- Timing
- no less than five days prior to earthmoving activities
- Intake B — North Delta
- Not StartedDue 2026-12-17
- Intake C — North Delta
- In ProgressDue 2026-08-26
- Bethany Reservoir Aqueduct
- Completed
Fund and Implement the DS/LFS Spawning Habitat Study
COA 10.21.5
At least one year before in-water construction begins, Permittee funds and implements, with CDFW, a study within the Abundance and Distribution Study that determines where Delta Smelt and Longfin Smelt spawn in the Sacramento River, the share of adults spawning upstream of the north Delta intakes, bank and low-velocity habitat use for adult and larval migration, and the substrate, velocity and salinity characteristics of spawning habitat.
- Frequency
- One time
- Timing
- At least one year before initiating in-water construction Covered Activities
- Intake C — North Delta
- Completed
- Bethany Reservoir Aqueduct
- In ProgressDue 2026-12-17