QA

Components

Preview

Component status

7 total
7
Components tracked
  • Not started 2
  • In progress 3
  • On hold 1
  • Complete 1

Needs attention

3
Components with overdue actions
  • Southern Forebay & Pumping Plant 3 overdue
  • Intake B — North Delta 2 overdue
  • Twin Cities Complex 1 overdue

All components

7
Sorted by: needs attention
Southern Forebay & Pumping Plant Forebay · Byron Tract
In progress
3 overdue actions

Regulating forebay and pumping plant at the southern terminus of the conveyance tunnel, feeding Bethany Reservoir.

Requirements 11 / 14 met
Actions 22 / 30 complete
Open actions 6 3 overdue
Work areas 7
Recent monitoring Jul 2 · 11 in 30d
Open component Updated 2 days ago
Delete this component and its rollups?
Intake B — North Delta Screened intake · Sacramento River
In progress
2 overdue actions

Two-bay cylindrical-tee screened intake on the Sacramento River near Hood, with fish-screen and sediment facilities.

Requirements 8 / 12 met
Actions 15 / 28 complete
Open actions 9 2 overdue
Work areas 5
Recent monitoring Jun 28 · 6 in 30d
Open component Updated 4 days ago
Delete this component and its rollups?
Twin Cities Complex Tunnel shaft · Staging
On hold
1 overdue action

Maintenance shaft and reusable tunnel material staging complex; work paused pending revised haul-route agreement.

Requirements 4 / 10 met
Actions 7 / 18 complete
Open actions 5 1 overdue
Work areas 3
Recent monitoring Jun 12 · 2 in 30d
Open component Updated 3 weeks ago
Delete this component and its rollups?
Intake C — North Delta Screened intake · Sacramento River
In progress

Third North Delta diversion intake, sited downstream of Intake B; screens under fabrication.

Requirements 6 / 12 met
Actions 10 / 26 complete
Open actions 12
Work areas 5
Recent monitoring Jun 30 · 8 in 30d
Open component Updated 5 days ago
Delete this component and its rollups?
Bouldin Island Launch Shaft Tunnel launch shaft
Complete

Tunnel boring machine launch shaft on Bouldin Island; construction complete, in post-construction monitoring.

Requirements 9 / 9 met
Actions 20 / 20 complete
Open actions None open
Work areas 4
Recent monitoring Jul 1 · 4 in 30d
Open component Updated 1 week ago
Delete this component and its rollups?
Bethany Reservoir Aqueduct Aqueduct · Alameda County
Not started

Aqueduct connecting the Southern Complex to Bethany Reservoir; requirements imported, field work not yet begun.

Requirements 0 / 9 met
Actions 0 / 14 complete
Open actions None open
Work areas 2
Recent monitoring No activity yet
Open component Updated 2 weeks ago
Delete this component and its rollups?
Byron Tract Forebay Forebay · Contra Costa County
Not started

Secondary forebay component; scoping in progress, no active requirements or monitoring yet.

Requirements 0 / 7 met
Actions 0 / 11 complete
Open actions None open
Work areas 1
Recent monitoring No activity yet
Open component Updated 1 month ago
Delete this component and its rollups?